Mobile factory, Viana do Castelo

CorPower C4 exporting power to Portuguese grid

Energize Editors

Energize Editors

CorPower Ocean’s first commercial scale Wave Energy Converter, the CorPower C4, continues to make rapid progress after its first seven weeks of operation off the coast of Aguçadoura in northern Portugal, accelerating through commissioning and exporting power to the grid.   

The main steps of the commissioning program have now been completed, verifying that the machine functions are operating as specified. All operational modes, including Storm Survivability, Derated and Tuned Production modes as well as Maintenance modes have been successfully tested.

In addition, the C4 device has shown its capacity to make autonomous decisions transitioning between different machine states according to ocean conditions, which are monitored by onboard sensors and control systems.

In the coming period, CorPower Ocean’s team will focus on ramping up the machine’s motion and power capture as focus shifts towards power performance tuning, while monitoring safe operation in storm conditions.

CorPower Ocean Chief Engineer Jonny Meason said: “We have been making steady progress after the installation in August , with initial focus on machine safety and survivability, to ensure robust operation in any kind of weather. Safety critical control and sensing functions have been successfully verified with the C4 enduring waves up to six meters. Power export to the Portuguese grid began on the same day as the required permit was received from authorities. After verifying power generation in tuned operation with limited motion envelopes, work to gradually allow the device to make increasingly larger motions and thereby capture more energy has been initiated. We look forward to providing further progress reports in due course.”

A key innovation which CorPower Ocean has brought to wave energy is its ‘WaveSpring’ phase control technology. When activated on the C4 device, the novel feature has been verified to significantly amplify the device motion, allowing it to make larger movements than the incoming wave height, which increases the power capture.

Remote monitoring and control has been performed from CorPower Ocean’s control centre, where the machine has initially been monitored 24/7. Surveillance is gradually being reduced to periodic check-ins as the commissioning program is advancing, with the control system sending alarms to operators in case of events that require attention.

The C4 device has been powered on during the entire period since grid connection in late August. The automatic transition into UPS (Uninterrupted Power Supply) mode – to keep critical sensing and control functions running in case of grid failure or intended isolation from the on-land substation has been successfully verified.  

Furthermore, methods for manned offshore O&M access have been tested and reviewed with third party safety reviewers, with CorPower technicians subsequently accessing the machine to perform internal inspections. 

Jean-Michel Chauvet, Director of Integration & Test added: “With the device operating successfully for more than seven weeks now, we are planning for a first disconnection in the near future, with tow-back to the nearby Port of Viana do Castelo for on-land check-up. After completion of this first on-land O&M cycle, the device will be towed back and re-connected to the site. Demonstrating efficient O&M supported by our modular approach to utility scale wave farms is a key goal of the C4 deployment program. The first disconnection and tow-back to port will be reviewed by Marine Warranty Surveyors who will ensure the work is performed to approved method statements, which is a requirement for wave farm insurability.”

Related Posts